根據環氧地坪漆廠家工程施工的相關經驗,在環氧地坪施工過程中有可能會出現以下幾種地面問題,環氧地坪漆廠家建議采用以下解決方案:一、混凝土表面有裂紋、脫皮、麻面、起砂等現象或有油污時的處理方案:如基礎地面小范圍出現輕微裂縫(不影響環氧地坪施工)時,對問題地面進行處理,有裂紋處使用光磊環氧涂料進行填充。
According to the construction experience of Guanglei Epoxy Floor Paint Factory, the following ground problems may occur during the construction of epoxy floor paint. The epoxy floor paint manufacturer suggests the following solutions: 1. Treatment schemes for concrete surface with cracks, peeling, flax, sand or oil contamination, such as slight cracks in a small area of foundation ground (without affecting epoxy). During floor construction, the problem ground is treated, and the cracks are filled with epoxy coating.
如地面出現脫皮、麻面及起砂部位打掃干凈后使用光磊環氧封閉底涂材料進行滲透加固處理,以增強基礎地面的附著力,脫皮及裂縫處使用環氧砂漿材料批補,以保證整體地面的平整度,我單位將根據基層加固使用材料情況收取相應加固材料成本費。
If the surface is desquamated, linen surface and sand-lifting parts are cleaned, the surface of the ground is strengthened by using glazed epoxy sealed primer material to enhance the adhesion of the foundation ground, and epoxy mortar material is used to repair the desquamation and cracks in order to ensure the levelness of the whole ground. Our unit will charge the cost of reinforcing material according to the use of the base reinforcement material.
特殊混凝土地面處理
Special concrete ground treatment二、基面含水率在6%以上時施工處理方案:
2. When the water content of the base surface is above 6%, the construction treatment scheme shall be as follows:
一般環氧地坪漆對基面含水率的要求是不高于4%,如果混凝土基面含水率高,而且又濕潮可選擇做泥找平層解決基礎地面含水量高和潮濕的問題;(成本另計)
Generally, epoxy floor paint requires no more than 4% moisture content of the base surface. If the moisture content of the concrete base surface is high and wet, mud leveling layer can be chosen to solve the problem of high moisture content and humidity of the base surface; (Cost added)
在含水率不是很高的情況下可做防潮層處理或者采用防水底漆做封閉材料,做好混凝土基礎地面的干燥工作。
When the moisture content is not very high, it can be treated as a moisture-proof layer or waterproof primer as a sealing material to do a good job of drying the concrete foundation ground.
如在鋪設混凝土基礎層時沒有做防潮層和防水層的情況下,可使用防潮類的環氧地坪漆施工,防水涂料封底,針對含水率不斷升高的的地面,說明地下水游上滲的趨勢,就需要做好徹底的防水封底。
If there is no moistureproof layer and waterproof layer when laying concrete foundation layer, we can use moistureproof paint construction, waterproof paint bottom sealing, in view of the rising water content of the ground, indicating the trend of groundwater upstream seepage, we need to do a thorough waterproof bottom sealing.
環氧地坪施工過程中,在混凝土基礎地面潮濕,含水率高的情況,在鋪設環氧地坪漆之前一定要按照以上的方法解決好含水率高的問題再進行施工,否則,會出現返潮,起水,脫層的現象。(防潮層根據現場具體情況另計)
During the construction of epoxy floor, when the concrete foundation is wet and the water content is high, we must solve the problem of high water content according to the above methods before laying epoxy floor paint. Otherwise, the phenomenon of moisture regain, water rising and delamination will occur. (Moisture-proof layer shall be added according to the specific conditions of the site)
環氧環氧地坪漆施工現場
Construction site of epoxy floor paint三、空氣中濕度在85%以上時施工處理方案:
3. Construction treatment scheme when air humidity is above 85%:
根據我單位環氧地坪施工經驗,在濕度超過85%時,地坪漆廠家建議使用水性聚氨酯地坪施工作業。
According to our unit's experience in epoxy floor construction, when the humidity exceeds 85%, Guanglei floor paint manufacturer recommends the use of waterborne polyurethane floor construction.